Day 58 Cont'd - Another Trip to the Millworkers
by Amber N. Yoo, M.B.A.
After the site visit today, Kelly Hinchman and I stopped by the millwork shop to check on the furniture that is being custom built for our 4S Ranch office. First, we looked at the progress on the credenzas that will be in the consultation rooms.

Day 58 - Cabinetry arrives!
by Amber N. Yoo, M.B.A.
It's Day 58 of construction on our new office in 4S Ranch and the cabinetry has arrived at the site for installation!
The cabinetry was built offsite according to the the "shop drawings" that are based off of the original construction documents and measurements taken at the site.
Right now, individual units (e.g. a stack of drawers) are sitting in various rooms of the new space, waiting to be unpacked and installed.

Day 54 - Let there be light!
by Amber N. Yoo, M.B.A.
More exciting progress at the 4S Ranch office! It's amazing what a fresh coat of paint will do to a space!

Day 45 - Walls are prepped for paint!
by Amber N. Yoo, M.B.A.
You are going to be shocked by the progress in today's post! (Well, I am at least.)
This week, the drywall is being prepped for paint. All of the seams where the drywall panels join together are covered with plaster in order to create a smooth, seamless wall to paint.